39 Muara Baru Dike Piles Have Been Installed
access_time September 16 2016 12:52 PM remove_red_eye 2057
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
Reported by Aldi Geri Lumban Tobing | Translated by Rizky Mawardi
The construction of sea dike for stage 2 package 1 at Muara Baru, Penjaringan, North Jakarta is started. At this moment, 39 dike piles have been installed along 50 meters.
Piles installation can reach two or three spots. The installation also depends on weather condition
Agus Priyono, project implementer, said the dike will be constructed along 1.8 kilometers and targeted to completed in mid 2018.
“Piles installation can reach two or three spots. The installation also depends on weather condition,” he said, Thursday (9/15).
This Year, Sea Dike Pole Targeted to Be Installed in April 2018He added that the pile has length by 24 meters and diameter is 1.2 meters. The pile is planted 17 meters under the sea and 3.5-4.5 meters above the sea.
He ensures the pile will be able to block tidal wave.
“It surely assist the surrounding residents,” he closed.